Lean To & Concrete Floor
Oct 29th, 2013, 6:10am
 
Currently have a 600mm wide concrete path and then mud.  This is going to be inside a lean to soon.  I want to put a DPM down and then concrete sand cement screed?

The ground slopes from one end to other by some 4 inches.  Ideally I will leave the path and the new concrete or screed will just go on top.  What sort of depth do I need to go to with concrete or screed on top?  What needs doing to the hard mud?  Gravel and whacker?

Thanks.
Back to top
 

Need to post a picture? Click HERE for info!
Thank User For This Post WWW View members image gallery  
IP Logged
 
woodsmith
Global Moderator
Trade Member
Author
*****
Offline


Posts: 4395


Total Thanks: 135
For This Post: 1


Gender: male

Trade: Joiner

Re: Lean To & Concrete Floor
Reply #1 - Oct 29th, 2013, 8:06am
 
I'd be worried that the new concrete would crack where there are changes in the sub base, ie along the line of the path.  Can you not dig the path up, dig out the entire area level then maybe put some of the broken concrete back in as hardcore?
Back to top
« Last Edit: Oct 29th, 2013, 8:06am by woodsmith »  
Thank User For This Post View members image gallery  
IP Logged
 
Lectrician
Administrator
Trade Member
Author
*****
Offline

Ask The Trades
Posts: 8814


Total Thanks: 108
For This Post: 0


Braunton, North Devon, United Kingdom
Braunton, North Devon
United Kingdom

Gender: male

Trade: Electrician



Re: Lean To & Concrete Floor
Reply #2 - Oct 29th, 2013, 8:37am
 
That was one of my concerns too TBH.  It just seems like a lot of work Sad
Back to top
 

Need to post a picture? Click HERE for info!
Thank User For This Post WWW View members image gallery  
IP Logged
 
CWatters
Super Member
*****
Offline

"Daddy fick it" says James

Posts: 5150


Total Thanks: 58
For This Post: 1


Gender: male

Re: Lean To & Concrete Floor
Reply #3 - Oct 29th, 2013, 8:50am
 
How much can you raise the level by? Could you go for a suspended timber floor (needs a ventilated void underneath)?

Will it be heated to allow use as a conservatory in winter?

Brick stub walls? Foundations for those?

I share others concerns about it cracking. Best take an angle grinder to the concrete and have it out.

Typical floor slab is normally something like..

150 mm of hardcore, 25-50 mm of sand, 1200 gauge membrane (plastic sheet), 100 mm concrete slab, >85 mm insulation, 60 mm screed

With some types of insulation you can do.

150 mm of hardcore, 25-50 mm of sand, 1200 gauge membrane,  >85 mm insulation, >100mm concrete (& rebar/mesh).

If you really want to leave the path then you might get away with it if you made really sure the hardcore areas were well compacted and used rebar/mesh in the concrete? The insulation would take up some movement. Don't plan on tiles though just in case.



Back to top
 
Thank User For This Post View members image gallery  
IP Logged
 
Lectrician
Administrator
Trade Member
Author
*****
Offline

Ask The Trades
Posts: 8814


Total Thanks: 108
For This Post: 0


Braunton, North Devon, United Kingdom
Braunton, North Devon
United Kingdom

Gender: male

Trade: Electrician



Re: Lean To & Concrete Floor
Reply #4 - Oct 29th, 2013, 3:49pm
 
It's only a shed, nothing homely.  I only want to raise it for two reasons - to combat the slope (not really an issue I guess), and to provide a DPM to keep it a little drier in there.

Back to top
 

Need to post a picture? Click HERE for info!
Thank User For This Post WWW View members image gallery  
IP Logged
 
CWatters
Super Member
*****
Offline

"Daddy fick it" says James

Posts: 5150


Total Thanks: 58
For This Post: 0


Gender: male

Re: Lean To & Concrete Floor
Reply #5 - Oct 29th, 2013, 9:24pm
 
Ok not so bad then.

Ideally remove the concrete path but you might get away without.

I think I'd dig out the soil and compact the ground with a wacker plate. Then say 4" of hardcore (crushed limestone is good) again compacted. the area of hardcore should be bigger than the slab by say 6" on all sides. Then a sand blind (also compacted) and a DPM. the DPM is also to stop water from the concrete soaking in and drying the mix before it sets. Then formwork for the concrete with the top level. I reckon you need at least 3" (4" is better) at the shallow end meaning 7" of concrete at the thick end.

If the base is bigger than the shed then you should really lay a coarse of bricks or sacrificial treated timbers with DPC on top to raise the shed off the slab eg to prevent any water that pooling around the edge rotting the floor.

Using hardcore to level the site instead of concrete might/might not be possible - Hardcore should be below ground or it can wash out from under the edges of the slab. One option might be to cut out parts of the path, lay small trench founds, build up in brick which will then both raise the shed and act to retain hardcore on the inside which fixes the level. You might then get away with less concrete. Say 3-4" all over.

lots of ways to skin a cat.