Quote:Hi
Additional Items:
1) Replace first floor joists 2.7m x5m room
2) Dig up concrete ( 1x1.5m)at rear of building to access drainage systems and connect new pipes, then reconcrete
3) Replace floor boards and joists under stairs
4) Underfloor heating, insulate and concrete kitchen floor (2.7m x 5m)
5) Strip external walls back to brick of 3 bed semi-detached house 860sqft and fully re-plaster (not the internal walls)
An additional question!
We had paid for skimming and making good the external walls but their condition was poor hence the decision to fully re-plaster. what is the difference in time between these two?
1. a day but then there's loads of associated work, taking ceilings down and putting them back, floor boards etc, so could easily end up a weeks work.
2. could be a couple of days
3. again could be a couple of days.
4. could be as much as a week (5days.)
5. tricky. but maybe 2 weeks.
The above is a real guess (estimate) and depends on a million and one unknown problems and obsticals.