1st fix usually includes everything, pipes cables, etc that are under floors, in walls, ceiling, lofts, etc.
Boiler pipes, gas, water, waste, etc is next before units are fitted, so once the walls are plastered you can get the boiler fitted and piped up, the electric services should also be connected or run into boxes before the tiler gets going.
Think about what goes before or after each operation. example, you have to plaster the wall before you can paint or tile? what do you need in place before you fit the kitchen sink? and so on.
|